OpenContracts

EKFB JV - Temporary mechanical and electrical systems - Tunnels

BIP Solutions Limited Complete Contract award update

Buyer
BIP Solutions Limited
Estimated value
£1,000,000 as published; Contracts Finder does not say whether VAT is included
Procedure
Competitive quotation (below threshold)
Category
Works
CPV code
31523000 Illuminated signs and nameplates
First published
24 May 2021
Last updated
19 Jan 2024
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

EKFB is seeking to appoint a competent sub-contractor to design, supply and install the temporary M+E package for the Green Tunnels, which includes, but is not limited to:
- power supply
- general and emergency lighting
- firefighting system (water supply and fire main)
- signage
- brackets

These will contribute in providing a healthy and safe environment whilst constructing 3no twin-bore cut-and-cover tunnels.

The temporary M+E should be in service from the commencement of the MWCC activities inside the tunnels and will remain until the permanent M+E is installed (by others). The installation should be done in multiple visits, following the construction sequence of the tunnels. These visits should be short and efficient to ensure the disruption of other activities is minimum.

Anticipated Programme

Greatworth - from Jan 22 (in stages)
Chipping Warden - from Sep 21 (in stages)
Wendover - from Jul 22 (in stages)

Awards

SupplierValueDateStatus
Not named - 17 Jan 2024 Active

Notices

  1. 24 May 2021 Tender notice
  2. 17 Jan 2024 Contract award
  3. 19 Jan 2024 Contract award update

Contracts Finder holds the official notices, with their documents and contact details.

Data