Decarbonisation Project at Royal Botanic Gardens, Kew (Jodrell and Melon Yard Decarbonisation Project)

The Board of Trustees of the Royal Botanic Gardens, Kew Planning Planned procurement

Buyer
The Board of Trustees of the Royal Botanic Gardens, Kew
CPV code
45000000 Construction work
First published
24 Feb 2023
Last updated
24 Feb 2023
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Royal Botanic Gardens, Kew ('RBG Kew') is a world-famous centre for botanical and mycological knowledge. With two inspiring gardens at Kew in west London and Wakehurst in Sussex, we enchant our visitors with the wonder of plant diversity. The RBG Kew mission is to be a globally recognised resource for plant and fungal knowledge, building an understanding of the world's plants and fungi upon which all our lives depend.

RBG Kew's impact on the environment (including climate and biodiversity) sits at the heart of RBG Kew's work. Our commitment to tackling the environmental emergency is identified in our  Manifesto for Change, Science Strategy, Sustainability Strategy, and Environmental Sustainability Policy, but also sits centrally to our day-to-day operational activities.

At Kew Gardens, both the Jodrell and Melon Yard buildings are served by three gas-fired boilers located in a dedicated, below-ground plant room, located outside the footprint of the building. Within the Jodrell, the boilers supply hot water, the AHUs and radiators. In addition, the boilers also supply heating to the Melon Yard Glass Houses. At present the systems are not separated'

Designs have been completed to replace dual-fire oil/gas burners with a bespoke air source/water source heat pump plant. Including, new HV (UKPN), LV switchgear, PV Array, AHU and associated plant to:

1 - Reduce carbon emissions by 633 Tonnes CO2 per year.
2 - Increase Kew's onsite generation of renewable electricity by 38,612 kWh per year.
3 - Reduce Kew's operational reliance on fossil fuels for heating our buildings.
4 - Increase electrical resilience due to upgraded substation capacity.
5 - Have minimal impact on users.

RBGKEW is now looking to appoint a Principal Contractor to undertake all works associated with the Jodrell Decarbonisation Project. In order to deliver this requirement RBGKEW are also undertaking early market engagement to test the experience and capability of the market in delivering our requirements.

For further information including an early version of the specification, and an early market engagement form along with some questions to your demonstrate capability and experience please contact Jamal Jimenez ([email removed]).

Additional information: How to apply

Follow the instructions given in the description for more information on how to apply for this opportunity.

Notices

  1. 24 Feb 2023 Planned procurement

Contracts Finder holds the official notices, with their documents and contact details.

Data