Estimated value
£75,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£116,868 as published, VAT not stated
Procedure
Other -
Category
Works
CPV code
45000000 Construction work
First published
31 Mar 2025
Last updated
31 Mar 2025
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

his project is for the design and reconstruction of approximately 15m length of Scrithwaite Wood Retaining Wall on the C5008, North of Broughton Mills.
The existing wall has partially collapsed, with an adjacent length being in an unstable condition. The wall retains approximately 2.1m (max) of land (public highway) above a steep inclined slope. The collapsed section of the wall has created a residual slope of consolidated material with a 1m vertical slope of exposed natural gravel material below the defined road construction.
The Contractor will be required to undertake the role of Principal Designer & Principal Contractor and fulfil their obligations in accordance with CDM 2015.
The Contractor will be required to design and construct the permanent engineered highway retaining wall.
The Contractor will be required to design and check temporary works as required e.g. provision of shoring for excavation.
The Contractor should consider the design period required for the temporary and permanent works, including Technical Approval to CG300 and Design & Check Certification - considered to be a Category 0 structure.

Awards

SupplierValueDateStatus
Metcalfe Plant Hire Ltd £116,868 31 Mar 2025 Active