Cutty Sark - Fall Prevention System
National Historic Ships UK Complete Contract details notice
- Buyer
- National Historic Ships UK
- Estimated value
- £120,000 excluding VAT; £144,000 including VAT
- Awarded value
- £91,331 excluding VAT where the notices give it
- Procedure
- Below threshold - open competition
- Category
- Works
- CPV code
35113300Safety installations- First published
- 14 Aug 2025
- Last updated
- 19 Nov 2025
- Legal basis
- Procurement Act 2023
Description
1.Royal Museums Greenwich (RMG) constitutes several Sites and Buildings across a large area within the Royal Borough of Greenwich. They encompass the National Maritime Museum (NMM), the Royal Observatory (ROG), the Cutty Sark (CS), and the Queen’s House (QH). These four world-class attractions sit at the heart of Maritime Greenwich in a UNESCO World Heritage Site.
2.Cutty Sark is a celebrated historic sailing ship launched 1869 and was fastest tea clipper of its time, it is now an award-winning visitor attraction in Greenwich, London. It is managed and maintained by Royal Museums Greenwich, who are based at the National Maritime Museum.
3.The dry dock on the bank of the River Thames at Greenwich received Cutty Sark by water in 1954. The dry dock was drained and Cutty Sark exhibited in the open air until its restoration 2006-2012 when it was enclosed around the waterline with a glass roof. The dry dock became a basement where visitors can walk around and under the ship’s hull and which holds a café, exhibitions and events space.
4.Cutty Sark requires regular cleaning, maintenance and conservation. Many of the required activities must be undertaken from on top of the glass waterline roof. These activities might be cleaning the glass roof itself, ship exterior inspections, conservation and repairs, or replacements of hull timber planks individually or in sections.
5.The work requires access onto the roof which creates a work-at-height issue. A Fall Prevention (Latchway) System is required for the safety of workers. An existing installed system is aged and can no longer be proven to comply with evolving regulations.
6.A replacement of the Fall Prevention System is required to be designed, fabricated and installed by the Contractor. This will be the Contractor’s design responsibility under this design and build contract. The system must be fitted to the historic ship’s hull which will require collaboration with the Employer’s appointed Structural Engineer and conservation team.
7.RMG seeks contractors who are accredited / approved fall arrest and prevention designers and installers to carry out this work.
8.The works must be completed by 31st March 2026.
To view this notice, please click here:
https://www.delta-esourcing.com/delta/viewNotice.html?noticeId=993765327
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Ethos Facilities ltd | £91,331 | 21 Oct 2025 | Active |
Contracts
| Contract | Value | Period | Signed | Documents |
|---|---|---|---|---|
| Contract 1Active | £91,331 | 27 Oct 2025 to 31 Mar 2026 | 21 Oct 2025 | Notice |