Ceridigion culvert flow gauging construction project management and site supervision

Mining Remediation Authority Complete Contract award

Buyer
Mining Remediation Authority
Estimated value
£31,478 as published; Contracts Finder does not say whether VAT is included
Awarded value
£31,478 as published, VAT not stated
Procedure
Call-off from a framework agreement
Category
Services
CPV code
71248000 Supervision of project and documentation
First published
30 Jan 2026
Last updated
30 Jan 2026
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

By way of supporting the delivery of the Frongoch construction contract, which has been
let by way of a Procurement Act 2023 compliant open tender, a contract is required for
the delivery of NEC project management and site supervision services.
The construction works will be delivered under the NEC4 Engineering and Construction Contract Main Option A.

The current proposed construction timescales are expected to
be 6 weeks of onsite works. Further design and construction details are provided in the Site and works information.

Awards

SupplierValueDateStatus
arcadis £31,478 23 Jan 2026 Active