C199 Rome Street Arches U154 - Installation of Security Doors

Cumberland Council Complete Contract award

Buyer
Cumberland Council
Estimated value
£47,133 as published; Contracts Finder does not say whether VAT is included
Awarded value
£47,133 as published, VAT not stated
Procedure
Other -
Category
Works
CPV code
45000000 Construction work
First published
11 Feb 2025
Last updated
11 Feb 2025
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

The Council is procuring a contract to install the security doors
to allow Cumberland Council to inspect Rome Street Arches
on spans 1-6 and 8-12. O.S. grid Co-ordinates 340145E;
555204N.
The works include: -
Ventilation grill installation where missing (approx.
10)
Install new security doors and carry out repairs to
walls as detailed in the specification.
The Eastern elevation of spans 1-4. Saw cut new
opening in existing blockwork and install new security
door as per the specification.
The Eastern elevation of spans 5 & 6. Saw cut new
opening in existing blockwork and install new security
door as per the specification. Removal of container
and re-site.
The Western elevation of spans 8 & 9. Saw cut new
opening in existing brickwork and replace the existing
door with a double door as per the specification.
Vegetation Clearance.
The Western elevation of spans 10. Replace the
existing door with a double door as per the
specification. Vegetation Clearance. Take down and
rebuild the end wall which is suffering from a lean.
The Western elevation of spans 11. Replace the
existing door with a new single door as per the
specification. Vegetation Clearance. Take down and
rebuild the end wall which is suffering from a lean.
The Western elevation of spans 12. Not suitable for a
standard height door. Build up wall and fit customised
door or inspection hatch as per the specification.
Vegetation Clearance.
Some sections of wall are missing/ damaged to spans
8-12. There is quite a bit of work required to the brick
end walls of spans 8-12.

The land adjacent to spans 8-12 is a little bit
overgrown, but easily accessible at the moment as the
vegetation has started to die down. We believe there
is hardened ground below, or at least there was in
1994. it's just built up with vegetation and debris
overtime. The contractor is required to excavate down
to hardened ground to give us a 2m clear strip
adjacent to the structure.

Awards

SupplierValueDateStatus
Cubby Construction £47,133 10 Feb 2025 Active

Notices

  1. 11 Feb 2025 Contract award

Contracts Finder holds the official notices, with their documents and contact details.