Boiler Refurbishment Works located at Dudley, Northfield and Willenhall Fire Stations
West Midlands Fire and Rescue Authority Complete Contract award
- Buyer
- West Midlands Fire and Rescue Authority
- Estimated value
- £224,000 as published; Contracts Finder does not say whether VAT is included
- Awarded value
- £260,000 as published, VAT not stated
- Procedure
- Not applicable
- CPV code
42160000Boiler installations- First published
- 22 Jan 2018
- Last updated
- 22 Jan 2018
- Rules
- Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds
Description
The Services Contractor shall supply, install, test and commission the installations as
detailed on the tender drawings and specifications. The contractor should employ skilled
personnel and specialist contractors as necessary to achieve the standards described.
The mechanical services shall include the following: -
1) Strip out and enabling works.
2) Gas Installation.
3) LTHW Heating Installation.
4) Building Management and Controls systems.
5) Thermal Insulation.
6) Testing and Commissioning
All design drawings and design calculations should be submitted for comments. All plant
shall be installed such that it complies with CDM and Health and Safety guidance on
access and good maintenance.
The new boiler installations shall take place at the following locations:
Dudley Fire Station
Burton Road,
Dudley,
West Midlands,
DY1 3BZ
Northfield Fire Station
South Road,
Northfield,
Birmingham,
B31 2RB
Willenhall Fire Station
Clarkes Lane
Willenhall,
West Midlands
WV13 1HT
Awards
| Supplier | Value | Date | Status |
|---|---|---|---|
| Senate (Mech) Ltd, Arrow Services (Midlands) Limited, Carter Synergy Ltd | £260,000 | 3 Jan 2018 | Active |
Notices
- 22 Jan 2018 Contract award