# Blue Corridors in channel obstacle works - Box Culverts

North York Moors National Park Authority · Active · Tender notice

- Buyer: North York Moors National Park Authority
- Estimated value: £205,000 (VAT not stated)
- Procedure: Open procedure (below threshold)
- Category: Works
- CPV code: 90700000 Environmental services
- First published: 13 June 2022
- Last updated: 13 June 2022
- Rules: before the Procurement Act 2023 (published on Contracts Finder)

## Description

2.1 Objectives of the Contract
The key objectives of the contract are to undertake easement works to the barriers, identified in Table
1.1, below. All easement works are scheduled to take place in 2022. Easements proposed to be
constructed are summarised below:
Easement Summary: Reference, Barrier Type, Easement Description:
Rye 18 Vented Ford Replacement with triple barrel 10 m long 1.25 m wide x 0.75 m rise
precast concrete rectangular box culvert
Esk 5 Vented Ford Replacement with triple barrel 10 m long 1.25 m wide x 0.75 m rise
precast concrete rectangular box culvert
Esk 13 Vented Ford Replacement with triple barrel 8 m long 1.50 m wide x 1.00 m rise
precast concrete rectangular box culvert
The appointed Principal Contractor shall be responsible for carrying out all elements of the
construction works subject to the approval of the Client / Project Manager.
This Pre-Construction Information (PCI) document should be read in conjunction with the Contract
Data including the Risk Register and design drawings for the project.
Planning and drainage consent for the works is currently in progress.
2.2 Scope of Works
The works are outlined below and detailed within the design drawings and shall be appointed under
one contract per package of easement works. This document details the works required to be
conducted at the easement.
This PCI provides health and safety information as part of the Construction (Design and Management)
Regulations 2015 (CD...d formation surface;
Place box culvert sections into required locations (invert of central culvert section to be
100mm lower than that of the 2 other culvert sections);
Apply jointing seals between culvert sections (as per box culvert supplier's recommendations);
Re-grade watercourse bed to tie in to proposed culvert invert levels, reinstate bed with
selected excavations or imported clean stone as directed on site;
Place clean stone to bed and banks immediately downstream of culvert outfall and set stone in
concrete bed for up to 2m downstream of culvert, as directed on site;
Backfill and compact to sides of installed sides of culverts as required;
Add dowel /bolt connection between box culvert and concrete slab above;
Place 150-250mm deep A252 mesh reinforced C40 concrete on culvert sections (and tying
into existing road surface);
Add sealant waterproofing above the reinforced concrete layer;
Cast in-situ concrete headwalls, with weepholes on downstream headwall, to tie-in to concrete
box culvert sections;
Add half battered double kerbs with transition kerbs at each end on upstream and downstream
headwalls;
Lay tarmac running surface (and tying into existing road surface);
Attach 1.1m high handrail on upstream and downstream headwalls;
Reinstate disturbed banks, tying into culvert headwall; and
Place armour stone to watercourse at culvert outlet and reinstate upstream bed to lowered
level.
Full details are supplied in the additional documents

## Notices

- 13 Jun 2022: Tender notice https://www.contractsfinder.service.gov.uk/Notice/80a74905-5a03-4818-a773-25213ef366dc

---