OpenContracts

BE24052 - Heat Network Technical Assurance Scheme (HNTAS) Shadow Service Provider

DESNZ Complete Contract award update

Buyer
DESNZ
Estimated value
£2,076,720 as published; Contracts Finder does not say whether VAT is included
Awarded value
£2,076,720 as published, VAT not stated
Procedure
Call-off from a dynamic purchasing system
Category
Services
CPV code
73200000 Research and development consultancy services
First published
13 May 2024
Last updated
8 Oct 2025
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

**Please note this is an award notice, not a competition. This contract has been awarded via the Crown Commercial Services - RM6313 - Demand Management and Renewables DPS **

The Department for Energy Security and Net Zero has a requirement to appoint a supplier to support the design and operation of the Heat Network
Technical Assurance Scheme (HNTAS) pilot programme.

The Energy Act 2023 provides for Ofgem to be appointed as regulator of the heat networks sector and grants Ofgem the power to authorise individuals to operate heat
networks and undertake supply activity. Ofgem will grant authorisation to a heat network operator, provided that the operator's network meets certain authorisation conditions. The
Energy Act provides for compliance with minimum technical standards to be included as one of these conditions. This lays the foundation for technical standards secondary
legislation which is expected to come into force in 2025 to introduce mandated minimum technical standards for heat networks (e.g. mandating requirements on water flow
temperatures, pipe insulation, etc). All heat networks (existing and new) across a range of different characteristics (large city sized district heating to single block communal
networks) will be in scope of this requirement.

To promote compliance with these minimum technical standards, we are developing a Heat Network Technical Assurance Scheme (HNTAS). The technical specification
which sets out the minimum technical standards that heat network suppliers will need to adhere to, and that will be subject to assurance, is being written and is expected to be
completed in early 2024. Work is also underway to develop the assurance processes themselves, i.e. the procedures to assess compliance. Together, the technical
specification and assurance processes represent normative documents, i.e. a set of documents describing what heat suppliers must do. Once legislation is in place, it is intended
to designate these normative documents as a Code, adherence to which will be required in regulation.

Awards

SupplierValueDateStatus
Talan UK & Ireland Limited £2,076,720 26 Apr 2024 Active

Notices

  1. 13 May 2024 Contract award
  2. 25 Mar 2025 Contract award update
  3. 8 Oct 2025 Contract award update

Contracts Finder holds the official notices, with their documents and contact details.

Data