OpenContracts

Bathroom Modernisation Programme 2019 - 2022

Swindon Borough Council Active Tender notice

Buyer
Swindon Borough Council
Estimated value
£5,100,000 as published; Contracts Finder does not say whether VAT is included
Procedure
Restricted procedure
Category
Works
CPV code
39144000 Bathroom furniture
First published
20 Dec 2018
Last updated
20 Dec 2018
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Bathroom Modernisation Programme 2019 - 2022
Swindon Borough Council is seeking a suitably qualified and experienced contractor to undertake the Bathroom Modernisation Programme to properties within the Swindon Borough Council housing stock.
The contractor will be required to undertake works such as:

• The removal of existing facilities.

• The supply and installation of new bathroom facilities.

• General bathroom modernisation and minor repairs.

• Making good to the structure and finishing's internally and externally as required.

Full details relating to the Works are provided in the tender documents.
Contract Period
The contract will be initially for a period of 36 months commencing 1st May 2019 with the option to extend for a further period of 12 months subject to satisfactory performance and budget availability.
To participate, Suppliers will need to Register as a Supplier with ProContract, www.supplyingthesouthwest.org.uk , then Register an Interest before obtaining access to the tender documents. In the event of difficulties registering as a supplier, please refer to the System Administrator Proactis support team [email removed]
Please note that this is a Restricted, two stage procurement and only the Selection Questionnaire is required to be completed during the first stage. The draft tender documents, which may be subject to amendments, are included for information at this stage. The formal tender documents will be issued to the shortlisted suppliers for completion and submission.
Selection Questionnaire Responses
Responses are required to be submitted no later than 18th January 2018, 12:00:00 hrs UK Local time via ProContract Tender Portal - www.supplyingthesouthwest.org.uk
Selection Questionnaire Clarifications
If you require any clarifications on the Selection Questionnaire, please submit these in writing via Messaging in ProContract Tender Portal, including the project reference and title clearly in the Subject title, by 8th January 2019, 12:00:00 hrs UK Local time. The Council's responses to these clarification questions will be issued periodically via Messaging in ProContract Tender Portal.

Notices

  1. 20 Dec 2018 Tender notice

Contracts Finder holds the official notices, with their documents and contact details.

Data