OpenContracts

Area 3 Asset Support Contract Awarded

Highways England Complete Contract award update

Buyer
Highways England
Estimated value
£120,000,000 as published; Contracts Finder does not say whether VAT is included
Awarded value
£120,000,000 as published, VAT not stated
Procedure
Open procedure (above threshold)
Category
Works
CPV code
45233139 Highway maintenance work
First published
18 Nov 2019
Last updated
18 Nov 2019
Rules
Before the Procurement Act 2023: the Public Contracts Regulations 2015 and earlier rules, or below their thresholds

Description

Routes for Roads Maintenance, Renewal and Improvement elements, and Technology Renewal and
Improvement elements:
A3 from a point approx. 2km south of M25 at Ockham I/C (Surrey) south to its junction with the
A3(M) (Hampshire) including operation and maintenance of the twin bore Hindhead tunnel. M3 from a
point approx. 2km south of M25 at Kitsmead Bridge (Surrey) south to its junction with the M27
(Hampshire). A3(M) in its entirety (Hampshire). A303 from its junction with M3 Junction 8 (Hampshire)
west to its junction with the A338 (Hampshire/Wiltshire boundary line).
M4 from Junction 5 (Berkshire) to M4 Junction 15 (Wiltshire). A404(M) from M4 Junction 8/9 to A404
(Berkshire). A404 from A404(M) (Berkshire) to M40 Junction 4 (Buckinghamshire). A308(M) from M4
Junction 8/9 to A308 (Berkshire). A34 from M3 Junction 9 (Hampshire) to M40 Junction 9
(Oxfordshire). M27 from Junction 1/A31 Cadnam, Hampshire to A27 Hilsea, east of Junction 12,
Portsmouth (incl. slips to M275 - Tipner Bridge). M271 from Junction A3057 Romsey Road Rdbt,
Hampshire (north of M27) to Redbridge Rdbt, Southampton (south of M27). A27 from M27 Hilsea
(east of the M275 link to Portsmouth) to A259 Junction Warblington, Hampshire. A31 (Hants) from
M27 Junction 1/A31 Cadnam, Hampshire to Kins Stream Bridge (west of Ringwood, A338 Ashley
Heath Junction). A31 (Dorset) from Kings Stream Bridge (west of Ringwood, east of A338 Ashley
Heath Junction) to A35/A31 Junction Bere Regis, Dorset. There is potential for parts of the network to
be passed to the neighbouring HA area commissions/Local Authorities during the lifetime of the
Contract.
Co-location with, facilities for and supervision/management of the Highways Agency Regional
Technology Maintenance Contract (RTMC)for the South East in Areas 3 and 4. The RTMC (SE) Network
in Areas 3 and 4 is listed below:
Area 3
A3 from a point approx. 2km south of M25 at Ockham I/C (Surrey) south to its junction with the
A3(M) (Hampshire) including operation and maintenance of the twin bore Hindhead tunnel. M3 from a
point approx. 2km south of M25 at Kitsmead Bridge (Surrey) south to its junction with the M27
(Hampshire). A3(M) in its entirety (Hampshire). A303 from its junction with M3 Junction 8 (Hampshire)
west to its junction with the A338 (Hampshire/Wiltshire boundary line). A34 route within Hampshire
boundary only. M27 from Junction 1/A31 Cadnam, Hampshire to A27 Hilsea, east of Junction 12,
Portsmouth (incl. slips to M275 - Tipner Bridge). M271 from Junction A3057 Romsey Road Rdbt,
Hampshire (north of M27) to Redbridge rdbt, Southampton (south of M27. A27 from M27 Hilsea (east
of the M275 link to Portsmouth) to A259 Junction Warblington, Hampshire. A31 (Hants) from M27
Junction 1/A31 Cadnam, Hampshire to Kins Stream Bridge (west of Ringwood, east of A338 Ashley
Heath Junction). There is potential for parts of the network to be passed to neighbouring HA Area
commissions/Local Authorities during the lifetime of the contract. Routes that are covered

Awards

SupplierValueDateStatus
Kier Transportation Limited £120,000,000 11 Jun 2013 Active

Notices

  1. 18 Nov 2019 Contract award
  2. 18 Nov 2019 Contract award update
  3. 18 Nov 2019 Contract award update

Contracts Finder holds the official notices, with their documents and contact details.

Data