Procurements

ProcurementStageValueUpdated
HRE - Closed Branch Lines Minor Works - SAD/26 - Combe Hay Road Bridge - Site Investigation Works Contract award £12,828 26 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - SYS/37 - Paint all structural steelwork Contract award £104,526 26 Oct 2023
HRE - Closed Branch Lines Minor Works - FBL/25 - Site Investigation Contract award £27,411 26 Oct 2023
HRE - Closed Branch Lines Minor Works - RWR/61 - Site Investigation Contract award £75,755 26 Oct 2023
HRE - Closed Branch Lines Minor Works - KAS/204, Whitehills - Site Investigation Contract award £42,496 26 Oct 2023
HRE - Closed Branch Lines Minor Works - KAS/149 - Site Investigation Contract award £60,622 26 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - ASE/13 - Replace broken and missing bricks along North East face rings Contract award £24,670 24 Oct 2023
HRE - Closed Branch Lines Minor Works - BBH/179 - Si and Ecology Assistance Contract award £15,952 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - TBY/26 - De-veg and Carry out steelwork surface preparation Contract award £185,427 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - MCJ3/430 - Fully remove trees in front of parapets Contract award £130,718 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - WMJ/34 - Paint steelwork as per the attached specifications Contract award £76,424 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - LEW/12 - Remove all delaminated / cracked concrete off the main beams Contract award £139,724 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - CLO/9 - Carry out pointing to abutments Contract award £114,798 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - RSD/46 - Repair spalled brickwork along soffit, piers, abutments, spandrels, parapets and wingwalls Contract award £46,720 24 Oct 2023
HRE - Closed Branch Lines Minor Works - WTD/1 - Site Investigation Contract award £14,640 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - DIC1/1 - Paint all structural steelwork as per the attached specifications Contract award £83,640 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - SWD/32 - Carry out patch pointing to abutments, wingwalls and parapets Contract award £105,004 24 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - HQU/6 - Carry out surface preparation Contract award £126,779 13 Oct 2023
HRE - Closed Branch Lines Minor Works - BAF/24 - Repairs in Detailed Examination Report Dated 12.11.20 Contract award £37,766 13 Oct 2023
HRE - Closed Branch Lines Minor Works - TJC3/119, Barrowford Road Bridge - Site Investigation Contract award £20,438 13 Oct 2023
HRE - Closed Branch Lines Minor Works - BRP/9 - Whetley Bridge - Site Investigation Works Contract award £16,844 13 Oct 2023
HRE - Closed Branch Lines Minor Works - MNG/35 - Repairs in Detailed Examination Report Dated 15.02.23 Contract award £50,523 13 Oct 2023
HRE - Closed Branch Lines Minor Works - GCL/39 - Various Security Improvements to GCL/35 to GCL/40L Contract award £46,472 13 Oct 2023
HRE - Closed Branch Lines Minor Works - DAK/68 - Repairs in Detailed Examination Report Dated 07.02.23 Contract award £42,015 13 Oct 2023
HRE - Closed Branch Lines Minor Works - ETC/259 - Repair the Defects Identified in the Detailed Examination Report Dated 09.02.22 Contract award £17,202 13 Oct 2023
HRE - Closed Branch Lines Minor Works - INL/50 - Repair the Defects Identified in the Detailed Examination Report Dated 08.03.22 Contract award £12,885 13 Oct 2023
HRE - Closed Branch Lines Minor Works - INL/59 - Repair the Defects Identified in the Detailed Examination Report Dated 08.03.22 Contract award £21,804 13 Oct 2023
HRE - Closed Branch Lines Minor Works - CKP/46 - Repair the Defects Identified in the Examination Report Dated 04.07.22 Contract award £21,721 13 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - COB/2m9ch Rhiw-ceiliog Road overbridge - Vegetation clearance for detailed exams Contract award £43,620 13 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - CAN 257m 60ch Pencader Tunnel - Aqueduct clearance Contract award £16,112 13 Oct 2023
HRE - Closed Branch Lines Minor Works - DAC/636 - Burn Lane Bridge - Refurbishment and Rewaterproofing Contract award £133,793 13 Oct 2023
HRE - Closed Branch Lines Minor Works - TRE/1 - Rejerrah Bridge - Fly-Tipping Removal and Fencing Contract award £21,792 12 Oct 2023
HRE - Closed Branch Lines Minor Works - Tet 95M 39CH, Culkerton Road Bridge Refurbishment Contract award £32,840 12 Oct 2023
HRE - Closed Branch Lines Minor Works - Tet 94M 72CH, Culkerton Road Bridge Refurbishment Contract award £34,989 12 Oct 2023
HRE - Closed Branch Lines Minor Works - GCT 126M 24CH, Bridge Works Contract award £59,735 12 Oct 2023
HRE - Closed Branch Lines Minor Works - TDZ 11M 31CH, Bridge Works Contract award £40,878 12 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - mbo 71M 55CH, BRIDGE WORKS Contract award £23,834 12 Oct 2023
HRE - Closed Branch Lines Minor Works - Ley 8M 78CH, Bridge Works Contract award £40,733 12 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - CDN 0m 14ch - osmond Bridge - site investigation and repair works Contract award £30,347 12 Oct 2023
HRE - Closed Branch Lines Minor Works - BHL 83M 30CH, Bridge Works Contract award £32,034 12 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - AGB/3 & 5 - Provision of high-level access for a Jacobs Ecologist to undertake exclusion works Contract award £10,778 5 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - SUX/4A, BRAMSHALL TUNNEL -SURVEY WORKS, Phase 2 Contract award £95,943 5 Oct 2023
HRE - Banbury and Cheltenham (Kings Sutton - Chipping Norton) Contract award £61,606 2 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - maj/289, castlefield north viaduct - descale, clear drainage troughs & install pigeon spikes Contract award £25,374 2 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - HHO/12 - Paint all structural steelwork and parapets Contract award £89,927 2 Oct 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - Dmb/5 - Provision of high-level access for a Jacobs Ecologist to undertake exclusion works Contract award £13,306 29 Sep 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - cal 4m 54ch - higher down Bridge - site investigation and repair works Contract award £32,253 22 Sep 2023
HRE - Closed Branch Lines Minor Works - CAL/21 - Chilsworthy Road Bridge - Refurbishment Contract award £127,839 21 Sep 2023
HRE - Closed Branch Lines Minor Works - Site Investigation Works at Multiple Bridges Contract award £32,094 21 Sep 2023
HRE - CLOSED BRANCH LINES MINOR WORKS - TNQ 4m 60ch - GOSHEN BRIDGE - REFURBISHMENT Contract award £143,370 21 Sep 2023

Value is what was awarded or contracted, otherwise the estimate, excluding VAT unless marked.

Top suppliers

SupplierAwardsValue
Amco Giffen54£2,264,935
Dyer And Butler54£1,871,785
Hammond48£2,579,262
Balfour Beatty30£2,034,312
Amco Giffen15£730,484
Amco Giffen11£1,045,684
Amco Giffen11£493,611
Bethell7£273,891
Bethell5£146,722
Hailsham Roadways Construction Co Ltd3£1,242,677

By number of awards. Value is the total of awards made to that supplier alone outside frameworks, excluding VAT where the notices give it.